The Helios Light Source

A hypothetical 3 GeV, 4th-generation synchrotron light source, with its EPICS control system designed end to end.

!!! warning “Helios is fictional” HLS does not exist. Its parameters are plausible and internally consistent — chosen in the spirit of published 4th-generation light source design reports — but every number here is a teaching device.

**Do not treat any value on these pages as a design value**, and do not treat any page here as safety guidance. Where these pages discuss machine or personnel protection, the point being made is [where EPICS stops](/EPICS-for-Dummies/docs/example-facility/machine-protection.html).

Why invent a facility

“You need a naming convention” teaches nothing. Watching a naming convention get chosen — with the 60-character Channel Access limit pressing on it, with third-party modules appending suffixes you don’t control, with a compromise for the machine protection system — teaches a lot.

So this section takes every architectural claim made elsewhere in this guide and forces it to survive contact with a concrete machine: 415 000 process variables, 330 IOCs, twenty beamlines, and an operations team who will be woken at 03:00 by whatever you get wrong.

The machine, in one table

   
Type 4th-generation storage ring light source
Energy 3.0 GeV
Circumference 528 m
Lattice 20 × seven-bend achromat (MBA)
Horizontal emittance 100 pm·rad
Stored current 500 mA, top-up every ~120 s
RF 500 MHz, two main cavities, passive 3rd-harmonic bunch lengthening
Injector 150 MeV linac → 3 GeV booster (concentric, same tunnel)
Insertion devices 15
Beamlines 20 (15 ID, 5 bending magnet) at full build-out

Full parameter set: Machine Parameters.

The control system, in one table

   
Process variables ≈ 415 000
IOCs ≈ 330
Network zones 6
Archived PVs ≈ 290 000, ≈ 24 TB/year at full resolution
Alarm-configured PVs ≈ 9 000, target < 10 annunciated alarms/hour
EPICS Base 7.0.x, both CA and PVA served
IOC deployment Container images, Kubernetes with host networking
Screens Phoebus, with DBWR for browser access

The chapters

Read in order the first time — each builds on the last.

Chapter The question it answers
Machine Parameters What is this machine, physically?
Subsystems What has to be controlled, and how fast?
Naming Convention What is every PV called, and why that scheme?
IOC Inventory 330 IOCs — which, where, and why drawn that way?
Network Design Six zones, five gateways: what crosses which boundary?
Service Deployment Where do the archiver, alarms and directory actually run?
Operator Interfaces What does an operator actually look at?
Archiving Plan Where does 24 TB/year come from, term by term?
Alarm Plan How do 9 000 alarms stay under ten per hour?
Machine Protection Where does EPICS stop, and why is that line absolute?
A Beamline BL07 in full: optics, detector, data, and its own IOCs
Operations Scenarios Startup, a 03:00 beam dump, a maintenance day
Build a Mini-HLS Run a shrunken version of all of it on your laptop

The design decisions, summarised

If you read nothing else, these are the choices the chapters argue for:

Location first in the PV name. SR-C05-PS-QF-01:Current-RB — section, then area, then device class. Because “everything in cell 5” is the most common operational query, and because gateway rules, archiver policies, alarm hierarchy and access-security groups are all written as name patterns. Why

Fine-grained IOCs. One per device group or crate, ~330 of them, not 20 large ones. Failure domains stay small and restarts stay cheap, which is affordable only because deployment is containerised. Why

Six network zones, and the office boundary is read-only by topology. Not by configuration, and not by access-security rules — by there being no path that can carry a write. Why

Monitor-based archiving with deliberate deadbands, set when records are created. Because ADEL lives in the IOC, and retrofitting it across a facility is much harder than thinking about it up front. Why

A three-level alarm hierarchy with delays on consequential alarms. So a beam dump produces one alarm at the top and a findable first cause underneath, instead of four thousand simultaneous red rectangles. Why

Protection systems are outside EPICS entirely. Certified PLCs and hard-wired logic; EPICS reads their status and cannot influence it. Why

Detector data never crosses Channel Access. Its own network, its own path to storage. EPICS controls the detector and supplies the metadata. Why

Next

Machine Parameters